Positive materials removed from a 1920s bungalow before its teardown
Example project
- Home
- 1920s bungalow in Long Beach with a detached garage at the back of the lot
- Original request
- Take the house down and build a new two-story home on the lot
- Testing
- A whole-house survey by a Cal/OSHA-certified asbestos consultant, about 24 samples from floors, ceilings, walls and the old heating pipes
- Found
- Asbestos in the kitchen and bath floor tile and mastic, the ceiling texture in three rooms and the wrap on the heating pipes
- Clear
- The plaster walls and the window putty
- Area
- About 420 sq ft of floor, 500 sq ft of ceiling and 20 ft of pipe wrap
- Timeline
- Notice no later than 10 working days ahead, then seven working days before the wrecking crew
- Cost
- $24,000
In this example, a family in Long Beach is replacing a 1920s bungalow with a new two-story house. Any demolition needs the district notice, so the whole-house survey comes first and the positive materials come out before the wrecking crew arrives.